Riding Team Repairs
Engine Repairs
Automation
PropellerShaft Seal Renewal
Steel Renewal
Cargo Crane Repairs
Boiler Repairs
Pipeline Fabrication
Ballast Tank Upgradation
Rudder Repairs
Towing Winch Retrofit
Safe Walkway for Tankers
Entire work is carried out by a team of 5-6 Riding Crew members during vessels ballast passage.
Retrofit period - 7 days.
Underdeck strengthening being provided for the Aft deck.
Wire Roller assembly being located and welded to the deck
Bow chain stopper aligned and being welded to forecastle deck, also Fairlead roller base being welded to deck from inside / outside.
Fairlead suitably strengthened by stiffeners and brackets welded around.
Fairlead being welded from shipside while sailing, after ensuring 100% safety precautionary measures for safe and sound working